Water Meter Plan Schedule 2009 - 2013
 

METERING PLAN

Date

Item Title

Summary Comments

01/09

Submit progress report to Bureau

U.S. Bureau of Reclamation

02/09

Secure installation contract for implementation

Begin implementation of consultant recommendations

08/09

Proceed with rate ordinance and Prop 218 process

Recommendation of a Uniform Single Tiered rate structure

10/09

Award contract for meters and meter reading system

Request Council to award contract and establish schedule

10/09

Initiate retrofit

Begin installation of meters on existing dwellings

11/09

Prop 218 Protest Hearing

Complete process and schedule required hearing

01-03/10

Metered Rate Implementation

(fees based on water usage)

Begin reading meters of those equipped with new meters and system. Rates effective as new installations occur.

10/10

Meter installation progress

29% (30,000 of approximately 105,000 units installed)

01/10

Submit progress report to Bureau

U.S. Bureau of Reclamation

10/11

Meter installation progress

62% (65,000 units)

01/11

Submit progress report to Bureau

U.S. Bureau of Reclamation

01/12

Submit compliance report to Bureau

U.S. Bureau of Reclamation

10/12

Meter installation progress

100% (105,000 units)

01/13

Submit completion report

Retrofit complete