City of Fresno Water Meter Plan Schedule
Water Meter Plan Schedule 2009 - 2013
|
|
METERING PLAN |
|
|
Date |
Item Title |
Summary Comments |
|
01/09 |
Submit progress report to Bureau |
U.S. Bureau of Reclamation |
|
02/09 |
Secure installation contract for implementation |
Begin implementation of consultant recommendations |
|
08/09 |
Proceed with rate ordinance and Prop 218 process |
Recommendation of a Uniform Single Tiered rate structure |
|
10/09 |
Award contract for meters and meter reading system |
Request Council to award contract and establish schedule |
|
10/09 |
Initiate retrofit |
Begin installation of meters on existing dwellings |
|
11/09 |
Prop 218 Protest Hearing |
Complete process and schedule required hearing |
|
01-03/10 |
Metered Rate Implementation
(fees based on water usage) |
Begin reading meters of those equipped with new meters and system. Rates effective as new installations occur. |
|
10/10 |
Meter installation progress |
29% (30,000 of approximately 105,000 units installed) |
|
01/10 |
Submit progress report to Bureau |
U.S. Bureau of Reclamation |
|
10/11 |
Meter installation progress |
62% (65,000 units) |
|
01/11 |
Submit progress report to Bureau |
U.S. Bureau of Reclamation |
|
01/12 |
Submit compliance report to Bureau |
U.S. Bureau of Reclamation |
|
10/12 |
Meter installation progress |
100% (105,000 units) |
|
01/13 |
Submit completion report |
Retrofit complete |
Schedule subject to change due to unforeseen circumstances.